Precision Lifting Success: Large‑Span Steel Grid Roof Hoisting Completed at Jakarta International Expo, Indonesia
Release time:
2026-06-26 19:02
Source:
On June 16, a major milestone was achieved at the steel structure project for the Jakarta International Expo (JIExpo) in Indonesia, undertaken by Luoyang Yu Metal Metal Structure Company. The project team successfully applied the super‑large component hydraulic synchronous lifting technology to complete the integral hoisting of a 9,041 m² large‑span welded‑ball steel grid roof. The entire operation was carried out safely and with all accuracy targets met, accumulating valuable practical experience for similar large‑span steel roof constructions.

The roof grid spans 70 m in total length, with a designed bearing elevation of 31 m and a total self‑weight of approximately 800 tons. It adopts welded‑ball joints and is a typical large‑span, heavy‑duty high‑altitude steel structure system. The conventional high‑altitude scattered assembly method wuld have required extensive temporary support frames at height, which entails significant high‑altitude work, long construction periods, difficult quality control, and high safety risks. Taking into account the site conditions and structural characteristics, the project team optimized the construction approach by adopting a ground‑level overall assembly plus hydraulic synchronous integral lifting scheme. By transferring key processes such as assembly and welding to ground level, the risk of falls and falling‑object accidents was fundamentally reduced from the source.

To ensure a flawless lifting operation, the technical team completed full‑process simulation verifications and prepared a dedicated lifting plan well in advance, with design and validation carried out strictly in accordance with applicable standards and specifications. Based on the grid's force‑bearing characteristics, 18 lifting points were arranged across the site. Depending on the load differences at each point, two models of hydraulic jacks—TLJ‑600 and TLJ‑2000—were deployed, along with specially matched 1860 MPa‑grade steel strands. The safety factor for all lifting jacks exceeded 1.25, and that for the steel strands exceeded 2.0, fully meeting regulatory requirements. In addition, steel lattice lifting frames, temporary members, lower suspension structures, and steel strand guide frames were installed to effectively prevent tangling and eccentric wear of the strands, thereby solidifying the hardware foundation for the lifting operation. Given the local meteorological conditions, the project team also formulated preventive measures against wind, rain, and typhoons, and developed contingency plans covering various emergency scenarios including hydraulic system failure, sudden power outage, falls from height, and falling objects. Emergency personnel and materials were fully prepared to ensure risks were controllable and incidents could be handled promptly.
The lifting process was powered by a TL‑CS 11.2 computer synchronous control system and a TL‑HPS60 hydraulic pump source system, which together formed a fully automated closed‑loop control system capable of real‑time monitoring of jack pressures and displacements. This enabled load balancing, attitude correction, fault alarms, and millimeter‑level precision adjustments. Throughout the construction, standardized procedures were strictly followed. First, the steel grid was fully assembled on the ground within its projection area, while the lifting frames, hydraulic equipment, and sensor systems were installed and debugged simultaneously. Next, a stepwise trial lifting was carried out with loads gradually increased from 20% to 100%. Once the grid was lifted 100 mm off the ground support frames, it was kept stationary in the air for more than 12 hours for comprehensive inspection of the structural and equipment conditions. After all checks were confirmed, the formal integral synchronous lifting commenced at a speed of 4 meters per hour. During the lifting, a dual‑control strategy combining "synchronized displacement + balanced oil pressure" was implemented on site. Professional surveyors continuously monitored and verified the grid's attitude and elevation differences at the lifting points, with real‑time fine‑tuning carried out through the control system. After the grid was precisely positioned at the designed elevation, the construction team proceeded with installing the infill members at the supports and conducting weld flaw detection. Once all post‑installed components passed inspection, a stepwise synchronous unloading process was carried out, releasing the load at each lifting point proportionally, while load transfer and displacement changes were monitored in real time. Subsequent inspections showed that all indicators—including mid‑span deflection, member stresses, and temporary structure deformations—met the design specifications and acceptance criteria. The strength, stiffness, and stability of all temporary structures such as lifting frames and embedded parts also fully complied with requirements.
The successful completion of this large‑span steel grid roof lifting at the Jakarta International Expo project fully demonstrates the efficiency, controllability, and safety advantages of hydraulic synchronous lifting technology in heavy‑duty, large‑span steel structure installation. It significantly improved construction efficiency, shortened the schedule, and reduced costs. Going forward, the project team will continue to focus on the final delivery target, strictly uphold safety and quality standards, and proceed with the subsequent construction at a high standard. With superior technical expertise and meticulous project management, the team is committed to ensuring the successful completion of the project and setting a benchmark for overseas steel structure projects, adding further luster to the "Henan Installation" brand on the international stage.